Project name
Railway Station
Location
CUMBRIA
Country
UK
Market area
BRIDGES

 

Requirement
Refurbishment of Station Steel work.
Surface Preparation
Surfaces degreased and pressure jetted to remove salt contamination prior to hand preparation to St3 standard of EN ISO 8501-1: 2007. Surfaces then steam cleaned to ensure full removal of salt contamination. Tests for salt carried out prior to coating.
Coatings
A primer coat of Corroless EPF and a top coat of Corroless RF65.Stripe coats were applied where appropriate for both coats
Product (per coat) DFT (per coat) Colour
Corroless EPF 200 microns Buff
Corroless RF65 50 microns varied

Comments
System has Network Rail Approval (XM92/M24-084) with an expected life of 15 years.