Project name
Fairground Equipment
Location
North Yorkshire
Country
UK
Market area
General Maintenance

 

Requirement
Severe breakdown of existing coatings was evident on fairground rides. The client wanted long term protection without the need to blast clean the steel.
Lead-free products were also a requirement.

Surface Preparation
Surfaces were degreased and then hand prepared to St2 standard of EN ISO 8501-1:2007, washed with fresh water and allowed to dry.
Coatings
A coat of Corroless S1 was followed by a coat of Corroless S2 as primers, with a topcoat of Corroless RF16 to complete the system.
Edges, welds, nuts and bolts were stripe coated before applying each full coat.